Depth and Pitch Test
The team successfully completed a stable depth and pitch test of the AUV. After tweaking the integral and derivative terms in our PID depth controller we were able to eliminate any oscillation and achieve a very acceptable settling time. The depth cell which was used for this test has a slight bias that caused a small amount of depth error but this problem will be rectified shortly when the new cell is installed.
Monday, April 6, 2009
Monday, March 30, 2009
Component Integration Tests Complete
All tests of the AUV components including the thrusters, DVL, depth cell, and compass are completed. Each of the ports had to be checked for pin-out order, voltage supplied and communication with the main computer to ensure that the vehicle is ready for water testing.
We are programming a demonstration plan for the AUV to include precision navigation using the compass and depth cell. The demonstration/test is scheduled for Friday and will show that our vehicle is completed and ready for operation. Naturally, we are going to continue to upgrade and perfect the programming and tasking for the vehicle but we will merely be making tweaks and improvements.
The frame is not going to be returned from the paint shop until thursday which means that we need to have the computer and programming ready for installation as soon as the frame is returned.
Tuesday, March 24, 2009
Looking Back...
After returning from break we weighed the AUV and were pleased when it weighed in at 38.92lbs. This is a significant improvement from last year's vehicle (yellow AUV above) which was 50lbs at the competition.
This was one of the primary objectives throughout the c
The frame was dropped off today for
Thursday, March 12, 2009
Wiring Is Complete
All major systems of the 2009 AUV nicknamed "Awkward Turtle" have been wired and connected to the computer and vehicle. Before all systems are powered up we are going to conduct a complete system voltage and continuity checks to ensure that all of our systems will not be overloaded or "fried". All of these check will be completed after spring break while everyone takes some much deserved time off and we prepare for the end of the semester.